PTC Annual Report for 2015: Peninsula Corridor Joint Powers Board

  • 20
  • Apr
  • 2016
AUTHOR: Peninsula Corridor Joint Powers Board / Caltrain
REPORT NUMBER: FRA-2010-0051
SUBJECT: Positive Train Control
ABSTRACT: The PCMZ and its System Integrator, Parsons Transportation Group have completed the construction phase of the project and have entered into the testing phase. Testing is being performed at multiple levels including lab, hi-rail and dynamic test train. We are actively engaged with FRA for approvals of prerequisite document for validation and verification activities, brake testing and onboard test plans.