ABSTRACT: SFRTA is still in the Procurement Phase for PTC. SFRTA is actively working with FDOT and CSX in order to resolve the indemnification issues associated with PTC 220, LLC and MeteorComm (see additional details below under Spectrum). Once these issues are resolved, SFRTA will advertise and begin the procurement process. As per SFRTA’s PTC Programming Schedule, a PTC Contractor should be under contract by late 2016. * SFRTA’s PTC Contractor will develop Track Segmentation plan following Notice to Proceed.